Update by Rachel Rutter
Good afternoon,
Within Plawsworth Sewerage Treatment Works the team have completed the wet well chamber and have excavated for the flow meter chamber. Reinstatement of fields will be undertaken when weather conditions are suitable including removal of timber bog mats and reinstate of field within easement area.
The air valve and discharge chamber are ready for construction and will begin in the next week, depending on weather conditions with the gravity sewer pipework now installed.
Thank you for your time. Please contact us direct if you have any questions at nwl.customer@esh.uk.com.
Have a great weekend!
Rachel