GENERAL PROJECT

WINEP Durham Transfer

As part of an £10 million scheme, Northumbrian Water will be carrying out essential works to improve the performance and flexibility of our wastewater network and wastewater treatment works in the Plawsworth, Pity Me and Brasside areas of County Durham. The scheme will help to improve the water quality of the Blackdene Burn for the benefit of people, the environment and wildlife and ensure that critical wastewater assets continue to serve the community effectively.

Project updates

Update by Rachel Rutter

Good afternoon,

The drainage outlet pipework from the flow meter chamber to the wet well chamber is ongoing with the air valve and washout chambers nearing completion.

As mentioned in the last update the gravity sewer pipework is now installed to the west side of the main railway line with a haul road created from the public highway to achieve access for the manhole construction.

Gravity Sewer Pipework is now installed from Brasside STW to the Outfall Structure. The woodland area will be reinstated once weather conditions begin to improve.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Good afternoon,

Hope everyone has had a lovely week!

The team this week have constructed the new flow meter chamber at Plawsworth Sewerage Treatment Works (STW) and wet well chamber within Pity me STW. The air valve and washout chambers are nearing completion from Plawsworth STW to Rotary Way.

The gravity sewer pipework is now installed to the west side of the main railway line with reinstatements to the fields being completed once weather conditions improve.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Good afternoon,

The concrete base and walls have been poured within the flow meter chamber at Plawsworth Sewerage Treatment Works.

Drainage works have begun at Pity Me Sewerage Treatment Works and the team are crossing fingers for suitable weather to reinstate the fields.

A haul road is completed on Chester Low Road to facilitate access, while reinstatement works to Brasside Sewerage Treatment Works are ongoing.

Thank you for your time. Have a great weekend!

Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Good afternoon,

Within Plawsworth Sewerage Treatment Works the team have completed the wet well chamber and have excavated for the flow meter chamber. Reinstatement of fields will be undertaken when weather conditions are suitable including removal of timber bog mats and reinstate of field within easement area.

The air valve and discharge chamber are ready for construction and will begin in the next week, depending on weather conditions with the gravity sewer pipework now installed.

Thank you for your time. Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Have a great weekend!

Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Good morning all,

I hope everyone is enjoying the little bit of sun we are getting.

This week the team are working on the directional drilled pipework for the Rising Main, which is nearly complete. The construction of the air value and washout chambers are ongoing to the A167m easement.

New pipework has been installed from the discharge chamber to Brasside Sewerage Treatment Works and the team are now working on the West side of the railway line installing gravity pipework towards Chester Low Road.

The team have begun preparation at Plawsworth Sewerage Treatment Works for the installation of foul sewer pipework.

Thank you for your time. Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Good afternoon all,

Hope everyone is well!

As mentioned previously the construction of the air value and washout chambers are ongoing.

New pipework has been installed from the discharge chamber to Brasside Sewerage Treatment Works, including drainage works within Plawsworth Sewerage Treatment Works.

The team continue to progress with work although the weather has been challenging.

Thank you for your time. Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Good morning all,

Hope everyone is well!

The Rising Main pipework and the Directional Drilled Pipework is partially complete.

Construction of the Air Value and Washout Chambers are ongoing along with the installation of a triple pipe in the single trench.

The Discharge Chamber to Brasside Sewerage Treatment Works has been installed, while work is ongoing on the gravity pipework towards Chester Low Road.

Drainage works within Plawsworth Sewerage Treatment Works are being completed for the installation of fouls sewer pipework with the wet well chamber installed.

Thank you for your time. Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Good morning all and a Happy New Year!

The directional drilled pipework for the Rising Main is complete and the crew continue to construct the air valve and washout chambers to the A167m easement.

Over the last few weeks, the team have installed 4.0meters diameter wet well chamber to Plawsworth Sewerage Treatment Works, cover slabs will be added at a later stage.

The crew continue to progress with work with some stages being completed in Spring 2024 due to design and weather conditions.

Thank you for your time. Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Good morning,

Hope everyone is well!

Direction Drilling works for the Rising Main sewer pipe continue between Plawsworth Sewerage Treatment Works and Hagg House Farm in agricultural land, with parts of the drilling completed and successfully installed.

The team have now drilled and installed pipework which incorporates drilling beneath A167M carriageway and up to the position of the proposed air valve chamber at top of hill.

Between Brasside Sewerage Treatment Works and Brasside Pumping Station pipework and chambers have been laid. To date approximately 528m of 400mm diameter gravity sewer has been installed and 5 new manholes constructed.

As you may have seen we have felled 15 large Poplar Trees adjacent to houses at Harvest View with an Ecologist present while the trees were removed. We will continue to keep residents in the area updated of any changes.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com or 0191 3774500.

Thank you

Rachel 

Please Login in order to comment on this update.

Update by Paul Davison

Despite the recent bad weather, we’re continuing to make progress with the installation of rising main and gravity sewer along various sections of the pipeline. Yesterday we successfully installed one of two rising mains under the A167 using  Directional Drilling methods. The drilling machine (Ditch Witch) located adjacent Pity Me Nursery sends an initial pilot drill hole beneath the A167 going west to east. Using an under pressure biodegradable drilling slurry, this keeps the drilled hole open while we attach a larger drill head which ‘back reams’ the hole to the size of the pipe.  Once the hole is ready to receive the new pipe, the Ditch Witch winches the welded plastic pipe back through the drill hole displacing the slurry.

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers