Update by Rachel Rutter
Good morning all,
Hope everyone is well!
The Rising Main pipework and the Directional Drilled Pipework is partially complete.
Construction of the Air Value and Washout Chambers are ongoing along with the installation of a triple pipe in the single trench.
The Discharge Chamber to Brasside Sewerage Treatment Works has been installed, while work is ongoing on the gravity pipework towards Chester Low Road.
Drainage works within Plawsworth Sewerage Treatment Works are being completed for the installation of fouls sewer pipework with the wet well chamber installed.
Thank you for your time. Please contact us direct if you have any questions at nwl.customer@esh.uk.com.
Rachel