GENERAL PROJECT

Whittingham Sewage Treatment Works Upgrade

We are investing £500k to improve the performance of our sewage treatment works at Whittingham. The work will involve an upgrade of the storm water storage provision. This will aid NWL in improving the quality of rivers and coastal waters for the benefit of people, the environment and wildlife.

Project updates

Update by Rachel Rutter

Good afternoon,

Hope everyone is well!

Following on from the weather we have had, the team are currently working on the permanent drainage connections and the manhole construction.

The team are working to schedule and fingers crossed we have better weather.

Thank you for your time. Have a great weekend!

Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Good morning,

Hope everyone has had a lovey week!

I would just like to take this opportunity to introduce a new member to the team, Alice will be working alongside Christine and I making sure customers are kept informed and to answer any queries.

You may have seen Alice and I in the area this week speaking to residents and seeing how the work progresses. Please don’t be shy if you see us, we are always happy to chat.

The team have been working to program this week despite the weather conditions and will continue to monitor throughout the work.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Thank you

Rachel & Alice.

Please Login in order to comment on this update.

Update by Rachel Rutter

Good afternoon,

This week the tank base has been completed and the team have constructed the wall shutters.

The walls have been poured ready for temporary use.

Over night starting Thursday 28 March 2024 a pump will be in use over the bank holiday weekend, we do not anticipate this to cause any disruption.

Thank you for your time. Have a great weekend!

Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Good afternoon all,

Our crew have begun work on the steel fixing within the site and by the end of next week, they will have completed the concrete pour.

I will be attending site next week and speaking to residents in the area regarding the work, if you see me please feel free to come over and have a chat.

Thank you for your time. Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Have a great week!

Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Good morning all,

Hope everyone is well!

As you may have seen works within the area have been progressing and the crew have completed the compound area and continue with the excavation for the new storm overflow tank.

Although the team have experienced ground water ingress, this has been easily managed with the right equipment. Next week the team will be starting the reinforcement to the base of the tank.

Thank you for your time. Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Good afternoon, 

Id like to take this opertunity to indroduce myself, my name is Rachel Rutter and I am the Customer Liasion working for Esh Stantec on behalf of Northumbrian Water. Some of you may have seen myself and my colleague Annah out on-site last week providing residents with an update for works to upgrade the sewer network.

The upgrade will increase capacity at the works, reducing the risk of pollution, and ensure this essential site continues to provide an effective treatment service for your home and the wider area.

All the work will take place within our site and will be undertaken by Esh Stantec. Although we do not anticipate any disruption for you, we just wanted to let you know that you may notice increased activity and more vehicles using the access route through the village, as well as a little more noise from the site.

The work will begin next month and will be limited to Monday to Friday, 8 am to 6 pm. We expect to complete our upgrade by the end of July 2024.

We will keep you informed as the work progresses.

If you have any questions or concerns, please comment on this post or email us on nwl.customer@esh.uk.com

Thank you 

Rachel

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers