Tunstall Reservoir Improvement Works

Together with our supply partners Esh Stantec we plan to carry out improvement works to Tunstall Reservoir during 2023. These works are needed to ensure the resilience of the reservoir.

Update by Rachel Rutter

Good afternoon,

The team have completed the concrete poor and have stripped the shutters from the discharge chamber.

Removal of the existing redundant main has begun in preparation for the installation of the outlet drainage.

Temporary access to the spillway has been removed and the work area reinstated.

Thank you for your time. Have a great weekend!

Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Rachel

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers