Good morning
As the weather has now started to improve, the team are starting to make progress with the spillway works and the last concrete pour will be being completed on Thursday.
The siphon drainage and discharge chamber are now being constructed which will be ongoing for the next 2/3 weeks.
You may also see the levels in the reservoir increase over the next few weeks as they are being closely monitored.
Thank you for your time. Please contact us direct if you have any questions at nwl.customer@esh.uk.com.
Rachel