Together with our supply partners Esh Stantec we plan to carry out improvement works to Tunstall Reservoir during 2023. These works are needed to ensure the resilience of the reservoir.

Update by Rachel Rutter

Good afternoon all and a Happy New Year!

Prior to the Christmas break the team were working on drilling operations while Northumbrian Water are continuing to lower and monitor reservoir levels to allow our essential works to be carried out.

The team continue to progress with work in order to install the siphon drainage. Reinstatements are being actioned where they can, to cause minimal disruption.

Over the next few weeks, the existing stone wall will be rebuilt, and the crew will continue with the installation of the spillway concrete slabs.

Thank you for your time. Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Rachel

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers